Case study · Energy infrastructure

Hydro Penstock Slope Protection

Soil nails and erosion protection to stop loose rock and small slips reaching a hydro power station's penstocks.

Location
Tuai, Hawke's Bay
Sector
Energy infrastructure
Year
2026
Penstock pipelines running down a steep slope with remediation works underway

Project overview

Small slips and falling rock from the steep slopes beside a hydro power station's penstocks, near Tuai in Hawke's Bay, were putting critical generation infrastructure at risk. A specialist slope contractor had been engaged to strip soil and loose rock from alongside the penstock, and asked Gibb Ritchie whether further protection was needed.

We inspected the slope as the work began, gave the contractor a concept solution on the day, then designed the permanent slope protection and stayed involved through installation.

Key challenges

  • Critical hydro infrastructure directly below the slopes being worked on
  • Weathered mudstone with layers dipping out of the slope, prone to sliding and loose rock
  • Rock quality that changed quickly across the slope, from strong to badly broken
  • Steep, remote terrain in a high rainfall area, needing specialist access

Our solution

Our first visit was during stripping, so we could see the exposed rock rather than rely on maps and photos. The rock was generally sound, but its layering dipped out of the slope and the side cuts held loose material. We gave the contractor a concept on the spot: protective mesh anchored back into the slope, with deeper anchors on the side cuts.

We then designed the permanent works: soil nails and erosion protection matting across the stripped face, and trimmed, nailed slopes where the cut ties back into the natural hillside. The design covered testing, inspection points and safe working at height.

Once the whole face was exposed, the rock proved far more variable than it first appeared. Rather than issue a fixed layout, we set simple rules for the contractor to adjust the nails to the ground they actually drilled into, and checked the first nails with them on site.

Stripped mudstone rock face beside the penstock
The stripped rock face beside the penstock
Spider excavator stripping soil and loose rock from the slope
Stripping soil and loose rock from the slope
Outcome

The contractor had a practical, buildable design that responds to the ground actually encountered, rather than a fixed layout that would be overbuilt in good rock and underbuilt in poor rock. The works protect the penstocks from loose rock and slips, and give the asset owner a clear basis for ongoing inspection and maintenance.